Month |
[kWh] |
---|---|
January |
2.500.625 |
February | 888.292 |
March |
857.048 |
April |
932.688 |
May |
642.831 |
June |
833.011 |
July |
760.535 |
August |
855.798 |
September |
1.198.987 |
October |
0 |
November |
0 |
December |
0 |
EISMAN |
0 |
Total |
9.469.815 |
Technical Data |
|
---|---|
Site |
Garlipp II |
Plant Type |
4x Vestas V112 |
Output per Plant [kW] |
3075 |
Hubhight |
94,0 m |
Annual Forecast [kWh] |
29.030.350 |
Commissioning |
13.06.2014 |